Schedule Planner

How far in advance do you actually need to order?

Enter your move-in date. We'll work backwards through furniture, construction, and everything you have to clear out of the old space — and tell you what's due when.

Your project

Takes about a minute
The day people need to sit down and work.
Drives install duration and crew size.
Ground-up fit-out or gut renovation with permits, MEP, and a GC.
The longest-lead item sets the schedule — not the average.
Sets the approval and procurement overlay.
Drives COI approval and freight elevator booking lead time.
Occupied space means phasing, swing space, and after-hours work.

Optional tracks

Planning aid, not a delivery commitment. Real dates depend on your actual products, building, lease, and approval chain — that's what a project manager nails down.

Prepared furngully.com

Furniture Schedule Plan

Working backwards from your move-in date — every decision deadline on the project, including the two most schedules miss.

Every date you have to hit

Plan-for dates sit at the conservative end of typical
Furngully · furngully.com · (508) 328-7939 · Estimate only — decision deadlines, not a quote
MilestoneTrackPlan forIf lead times slipWhy

Watch these

Where these numbers come from

Published
Manufacturer lead time pages, quick-ship programs, MA Chapter 30B thresholds, IBC and NFPA code limits. Verifiable and linked.
Furngully data
Install crew productivity, receiving and staging, substantial-completion-to-install lag, and residual value — from our own project history.
Industry estimate
Replacement part lead times, furniture audit duration, and discovery phase length. Nobody publishes these. This is our read, and we'll tell you when it moves.

What this tool doesn't know about your project

  • Your building's specific COI wording, freight elevator rules, and after-hours policy
  • Your lease's surrender, restoration, and holdover terms
  • Your manufacturer's current backlog on the specific lines you're speccing
  • How your AHJ reads pod, partition height, and sprinkler requirements
  • Your organization's real approval calendar and who has to sign
This is a planning aid, not a delivery commitment. Dates are ranges based on typical conditions and should be confirmed against your actual products, building, lease, and approval process before anyone commits to them. Lead times move constantly — verify with your dealer before a date goes in a contract.
Lead time and market data current as of · reviewed monthly

This is an estimate, not a quote

Every date here is a decision deadline derived from typical lead times and typical approval cycles as of . It is not a quote, a reservation of production capacity, or a commitment to a delivery date. Real lead times move with the specific products you spec, your building’s rules, your landlord’s approvals, and what the factories are running that month. Nothing in this document should go into a contract, a lease negotiation, or a construction schedule without being confirmed against actual quoted availability.

Bring us the drawings and we will pressure-test these dates against what is genuinely available right now.

Furngully
45 Industrial Park Road, Suite 2
Hingham, MA 02043
(508) 328-7939
furngully.com
furngully.com/contact/

Take this with you

Nothing here is gated. Save the plan, or hand us the numbers you just built and we'll check them against what's actually available.

The PDF is the whole plan, formatted. “Pressure-test” carries these dates over to a short form so you don’t retype them.